
- Targets
- History and background
- Location and general layout
- River specifications
- Features
Targets
- Providing balance in power network of the country in high-load and low-load hours
- Generating hydro-electric energy with a capacity of 1040 MW during peak hours
- Consumption of electrical power with a capacity of 960 MW during low-load hours
- Decreasing annual amortization expenses of thermal power for almost 19 million $
History and background

Location and general layout

- 125 kilometer north of Tehran
- 10 kilometer north of Kandovan tunnel
- Adjacent to Siah-Bisheh village
River specifications
Features
- The first pump storage power plant of Iran
- The first rock-fill dam with concrete lining in Iran
- Close distance of the project to Tehran as the biggest consumer of electricity
- About 20 years of engineering studies by Iranian and foreign consulting engineers
- Non-dependence on potable and agricultural water
- Small volume of reservoir and low environmental, economical, social and reservoir damage side effects

- Topography
- Meteorology
- Hydrology
- Flood
- Water quality
- Sedimentation
- Planning the water resources
- Geology
- Seismicity
- Dam reservoir
Topography

Meteorology

Temperature degree |
Downstream dam |
Upstream dam |
Maximum |
+ 25 |
+ 34.5 |
Miniimum |
- 18 |
- 27 |
Hydrology
With increasing altitude, generally downpours increase. Measuring downpours rate is a hard task due to dispersion of the catchment area and different distances of pluviometer stations.
In project area, maximum amount of downpours happen between February and March to May and June; that is 300 mm.
Average inflow discharge of downstream dam reservoir is estimated 67.1 m3/s. Outflow discharge of upstream dam is divided into two catchment areas. Differences of average downpours between Gramroodbar river (annually 400 mm for downstream part of the catchment area) and north of Kandovan (annually 950 mm for upstream part of the catchment area) would affect the current features.
Average of inflow discharge of upstream and downstream dams’ reservoir
Area of catchment |
Inflow current in 1990 to 1991 |
Average of inflow current |
|
Downstream reservoir |
93.8 hecto m2 |
23.6 hecto m3 annually |
49.2 hecto m3 annually |
Upstream reservoir |
19.3 hecto m2 |
6.5 hecto m3 annually |
13.5 hecto m3 annually |
Flood
The amount of flood for return period of 1000 years
in downstream and upstream reservoir
|
Average daily outflow discharge |
Maximum outflow discharge |
Downstream reservoir |
120 m3/s |
240 m3/s |
Upstream reservoir |
38 m3/s |
76 m3/s |
in downstream and upstream reservoir
Quarry |
Average daily outflow discharge |
Maximum outflow discharge |
Downstream reservoir |
165 m3/s |
330 m3/s |
Upstream reservoir |
53 m3/s |
106 m3/s |
Maximum 20 year flood |
Maximum 100 year flood |
The results of the year 1983 with the return period of 20 years |
|
Downstream reservoir |
74 m3/s |
1415 m3/s |
360 m3/s |
Upstream reservoir |
24 m3/s |
45 m3/s |
80 m3/s |
Maximum discharge with the return period of 10000 years |
PMF/PMP |
Ratio |
|
Downstream reservoir |
330 m3/s |
910 m3/s |
2.74 |
Upstream reservoir |
106 m3/s |
190 m3/s |
1.8 |
Water quality
Average suspended particles within Alborz mountains area is altering considerably and is within an approximate range of 300 ton/year/km2 to 200 ton/year/km2.
On the basis of carried out measurements near the area of downstream dam (Chalus river in Zoghal bridge and Karaj dam), total amount of sediments are almost 750 ton/Year/Km2.
Carried out estimation by the Lahmeyer-Moshanir J/V shows an amount of 1.09 ton/m3 for dried weight of settled sediments (10% sand, 45% slime, and 45% clay).
Sedimentation
Annual average of sediment erosion in upstream reservoir is 1118 ton/km2 and in downstream reservoir is estimated to be 660 ton/km2. These results show that annual estimated erosion in upstream catchment area is 170% more than downstream catchmnet area.
Planning the water resources
According to the nature of pump storage dams, always a definite volume of water dislocate between upstream and downstream reservoirs. The important issues related to water resource planning in water filling and operation periods of such projects can be generally as follows:
1- Water filling period:
In this period generally the upstream reservoir is filled up to the maximum operation level and it is necessary to fill the downstream reservoir to the minimum operation level. Also the water rights and environmental issues of the mentioned reservoir downstream should be considered.
2- Operation period
In this period, parts of daily outflow of the river which is surplus to the upstream reservoir profitable volume, would be used in power generation system and other parts would be released for the minimum needed water rights of downstream area in the river. Also in downstream reservoirs, releasing the compulsory surplus water which is from upstream reservoir and releasing the inflow of downstream reservoir water from two rivers of Garmrudbar and Chalus for keeping the reservoir at the minimum operation level and preserving needed empty volume of reservoir are among the important issues.
According to the considerable volume of water surplus, which is evacuated daily through the bottom outlet of downstream reservoir, some arrangements can be considered such as turbine installation in the exit of bottom outlet for optimum use of water.
Geology
Siahbishe project is located in north of Iran, between Tehran and Chalus cities and is situated in northern Alborz mountain domain which is part of the parallel anticline and synclines that form the southern boundary of the Caspian puddle. Siahbishe project is located in 4 kilometer distance of Candovan trust fault which is very important in technical structure of Iran geology. It devides Alborz chain mountains into two northern and southern parts. In southern part, Karaj Sazand is expanded with Sansenozoic and in its northern part, where Siah-Bisheh project is located; the Sazands of first and second geology periods are expanded.
Seismicity
Some of the important faults of the Siahbishe dam structures are Candovan, Talaghan, northern Alborz, north of Tehran, Caspian and the main fault of the construction area. The biggest earthquake of this zone has been 7.4 in Richter scale and the biggest earthquake resulted from the nearest fault (Candovan) has been 7.2 in Richter scale.
The biggest earthquake velocity which is sustained into the construction area is about 0.59 g horizontal in downstream dam zone and 0.41 g vertical in upstream dam zone.
Achieved velocity for operation base level is equal to 0.25 g horizontal and for maximum design level is equal to 0.34 g horizontal.
Dam reservoir
Temperature degree |
Downstream dam |
Upstream dam |
Minimum operation level |
2376 masl |
1885.5 masl |
Maximum operation level |
2407.6 masl |
1905.2 masl |
Profitable reservoir volume |
3642858 m3 |
3707105 m3 |
Length of reservoir |
1000 m |
1100 m |
In this section the technical information of the project is presented in form of the following items:
- Dam body
- Body specifications
- Reservoir specifications
- Diversion systemInstrumentation
- Spillway
- Quarries and their specifications
- Powerhouse
- General specifications of powerhouse
- Specifications of powerhouse equipments
- Specifications of powerhouse building
- Specifications of powerhouse outlet tunnels
- Specifications of powerhouse waterways
- Technical specifications of post and switchyard
- Water transfer tunnels
- Specifications of tunnels
- Intake structures
- Outlet structures
- Access roads and bridges
- Complementary operations
Body specifications
Upstream Dam
Item |
Quantity |
Dam type |
Rock-fill with concrete lining (CFRD) |
Height from foundation |
82.5 m |
Crest length |
436 m |
Crest width |
12 m |
Foundation width |
280 m |
Total volume of the body |
1.55 million m3 |
Total volume of concrete placement |
13506 million m3 |
Downstream Dam
Item |
Quantity |
Dam type |
Rock-fill with concrete lining (CFRD) |
Height from foundation |
102 m |
Crest length |
332 m |
Crest width |
12 m |
Foundation width |
360 m |
Total volume of the body |
2.3 million m3 |
Total volume of concrete placement |
14057 million m3 |
Reservoir specifications
Upstream Dam
Item |
Quantity |
Total volume of reservoir |
4344220 m3 |
Area of reservoir |
141.105 km2 |
Length of dam lake |
1000 m |
Width of dam lake |
400 m |
Normal level |
+2406.5 m |
Item |
Quantity |
Total volume of reservoir |
6874709 m3 |
Area of reservoir |
234.284 km2 |
Length of dam lake |
1100 m |
Width of dam lake |
1000 m |
Normal level |
+1905.4 m |
Diversion system
Upstream Dam
Item |
Quantity |
Item |
Quantity |
Location |
Right abutment |
Excavated diameter after lining |
2.95 m |
Numbers of diversion tunnels |
1 |
Volume of open-cut excavation |
|
Length of diversion tunnels |
594 m |
Volume of underground excavation |
3935 m3 |
Cross section |
Circular |
Discharge capacity |
22.9 m3/s |
Type of lining |
Concrete |
Type, height and volume of upstream cofferdam |
Rock-fill |
Excavation diameter of tunnel |
2.95 m |
Type, height and volume of downstream cofferdam |
Item |
Quantity |
Item |
Quantity |
Location |
Right abutment |
Excavated diameter after lining |
4 m |
Numbers of diversion tunnels |
1 |
Volume of open-cut excavation |
|
Length of diversion tunnels |
707 m |
Volume of underground excavation |
8792 m3 |
Cross section |
U shape |
Discharge capacity |
32 m3/s |
Type of lining |
Concrete |
Type, height and volume of upstream cofferdam |
Rock-fill |
Excavation diameter of tunnel |
4 m |
Type, height and volume of downstream cofferdam |
Instrumentation
Upstream Dam
Item |
Quantity |
Ross Arm Extensometer (UEX) |
Surface Displacement Point |
Vertical joint Meter (UJM) |
Surface Displacement Point |
In Place Inclinometer (UIM) |
Vertical Inclinometer & Settlement Measurement (UISM) |
Perimeter Joint Meter (UPM) |
Hydraulic Settlement Cell (UHS) |
Total Pressure Cell (UEP) |
Electro Levels (UEL) |
Electrical Piezometer (UPP) |
|
Downstream Dam
Item |
Quantity |
Ross Arm Extensometer (UEX) |
Surface Displacement Point |
Vertical joint Meter (UJM) |
Surface Displacement Point |
In Place Inclinometer (UIM) |
Vertical Inclinometer & Settlement Measurement (UISM) |
Perimeter Joint Meter (UPM) |
Hydraulic Settlement Cell (UHS) |
Total Pressure Cell (UEP) |
Electro Levels (UEL) |
Electrical Piezometer (UPP) |
|
Spillway
Upstream Dam
Item |
Quantity |
Type of spillway |
Free staircase |
Location |
Left abutment |
Discharge capacity |
203 m3/s |
Length of chute |
490.3 m |
Width of chute |
20 m |
Item |
Quantity |
Type of spillway |
Free staircase |
Location |
Left abutment |
Discharge capacity |
860 m3/s |
Length of chute |
198.25 m |
Width of chute |
30 m |
Quarries and their specifications
Upstream Dam
Quarry |
Specifications |
Quantity |
Quarry no.1 |
Volume of exploitable rock |
1.981 million m3 |
Quarry |
Specifications |
Quantity |
Quarry no.2 |
Volume of exploitable rock |
0.83 million m3 |
Quarry no.3 |
Volume of exploitable rock |
1.8 million m3 |
General specifications of powerhouse
Item |
Quantity |
Type of powerhouse |
Underground Pump Storage |
Capacity |
1040 mw |
Average annual generation |
|
Turbine type |
Francis |
Specifications of powerhouse equipments
Item |
Quantity |
Numbers of turbine |
4 units |
Power of each turbine |
260 mw |
Maximum output |
97 % |
Height of turbine design |
504 m |
Discharge of each unit at manufacturing time |
65 m3/s |
Discharge of each unit at generation time |
50 m3/s |
Turbine manufacturer |
Foit Siemens Fuji |
Numbers and capacity of main transformers |
13 by 105 mva |
Numbers and capacity of auxiliary transformers |
3 by 10 mva |
Transforming ratio of main transformers |
18 kw/400 kv |
Impedance of short circuit |
12 to 14 % |
Numbers and type of generators |
4 units synchronic |
Output power of each generator |
260 mw |
Nominal voltage of each generator |
18 kv |
Rotation speed of generator |
500 rotations per second |
Nominal voltage of generator |
12500 Ampere |
Generator manufacturer |
Siemens |
Capacity of emergency generator |
1.9 mw |
Type of emergency turbine |
Diesel |
Cooling system of transformers |
OFWF (ODWF) |
Nominal frequency of transformer |
50 hertz |
Specifications of powerhouse building
1-Powerhouse cavern:
Length |
Width |
Height |
131 m |
34.5 m |
46.5 m |
Length |
Width |
Height |
160 m |
13 m |
22 m |
Length |
Width |
Height |
79 m |
4.5 m |
8 m |
Specifications of powerhouse outlet tunnels
In this regard no data exists.
Specifications of powerhouse waterways
In this regard no data exists.
Technical specifications of post and switchyard
Item |
Quantity |
Item |
Quantity |
Type |
GIS |
Numbers of high voltage lines |
3+1 |
Voltage level |
400 kv |
Numbers of intake feeders of XPLE cable |
4 |
Specifications of tunnels
Item |
Quantity |
Numbers |
2 |
Cross section |
Circular |
Diameter of each water transfer tunnel |
5.7 m diameter of concrete cross section |
5 m diameter of metal |
cross section |
Excavation diameter |
6.9 m |
Length of left tunnel |
2225 m to tank surge |
Length of right tunnel |
2185 m to tank surge |
Lining type of left water transfer tunnel |
2040 m concrete lining |
Lining type of right water transfer tunnel |
1985 m concrete lining |
Water transfer capacity of each tunnel at turbine status |
130 m3/s |
Water transfer capacity of each tunnel at pumping status |
100 m3/s |
Diameter if leaning shafts |
5 m |
Length of each leaning shaft |
540 m |
Lining type of leaning shafts |
Metal |
Diameter of outlet tunnel |
6 m |
Intake structures
Item |
Numbers |
Dimensions (m) |
Weight (Ton) |
Emergency intake gates |
2 series |
5.1 by 5.4 |
25 |
Fixing gates |
1 series |
5.2 by 5.4 |
17 |
Trash racks |
2 series |
10 by 14 |
34 |

Item |
Numbers |
Dimensions (m) |
Weight (Ton) |
Emergency outlet gates (Bulkhead) |
2 series |
5.3 by 7.1 |
18.4 |
Trash racks |
2 series |
9.5 by 13.6 |
32 |
Access roads and bridges
1- Technical specifications of access roads
Upstream Dam
Name of the road |
Average width (m) |
Length (km) |
Access road from Chalus road to upstream dam |
8 |
1499 |
Access road to bottom outlet from upstream dam crest |
8.7 |
1171 |
Access road to surging tanks through upstream dam crest |
10.5 |
3000 |
Access road to entrance of bottom outlet through upstream dam crest |
11 |
878 |
Access road to intake gates chamber through upstream dam cerst |
Name of the road |
Average width (m) |
Length (km) |
Access road to Daryabak Complex from Chalus road |
7 |
2365 |
Access road to dam crest from Daryabak road |
10 |
380 |
Access road to area of GIS post |
7.9 |
750 |
Connection road between the downstream and upstream dams This road passes near the entrance of main access tunnel and ends to the access road to surging tank of upstream dam |
7 |
4030 |
Access road to AGC |
7 |
1000 |
Access road to NAG |
7 |
1800 |
Access road to middle access gallery to pressure shafts (Intermediate Adit) |
1 |
1700 |
Access road to surging tanks |
7 |
4030 |
Access road to substitute chamber in waterways |
7 |
520 |
Access roads to consultant and client offices |
7 |
550 |
Access road to contractor office (Joint B) |
7 |
1200 |
Access road to entrance of bottom outlet through downstream dam crest |
6 |
500 |
Access road to exit of bottom outlet through downstream dam crest |
Name of the bridge |
Width (m) |
Length (m) |
Type of structure |
The bridge on chute of upstream dam |
7.5 |
21.6 |
Metal with concrete lining (Composite) |
The bridge on chute of downstream dam |
6.2 |
31.5 |
Metal with concrete lining (Composite) |
The bridge on Garmrudbar river |
8 |
62 |
Metal with concrete lining (Composite) |
Complementary operations
In this regard no data exists.