In this section the project is introduced in form of following items:
Targets
- History and background
- Location and general layout
- River specifications
- Specifications of catchmnet area
- Dam location
- Features
- Side effects
Targets
Generating hydroelectric energyTargets
- Preventing Bakhtyari River sediments from entering into dam reservoir and therefore increasing life-time of Dez dam and power plant
- Controlling floods, preventing its annual destruction and improving the conditions
- Safety measures in downstream of dam
History and background
History & background of the projectThe preliminary studies about Bakhtiari project started in March 1996 by Mahab Qods Consulting Engineers and continued for about 33 months. Related reports of the first phase of the project were handed over to the client (IWPC) in March 2000.
After electing the project manager in 2004 and transferring the management of the project from IWPC deputy department, negotiations related to electing the consultant of the second phase of the project continued and finally in May of 2005, IWPC handed over the consulting services of the project (including review and completion of the first phase studies, the second phase studies and preparing tender documents) to the following group of consultants:
- Moshanir Consulting Engineers
- Dezab Consulting Engineers
- Econo-Electrowatt (Swiss)/ Boyri joint-venture
- Stucky Pars Consulting Engineers
- with common and individual responsibilities.
Location and general layout
Construction location of Bakhtiari dam and power house is in downstream of the Bakhtiari River in Lorestan Province, in south-western parts of Iran and in south-western domain of Zagros Mountains; in a zone with eastern longitude of 48°, 46' and 50" and northern latitude of 32°, 57' and 41"; which is situated in north-west of Tangpanj station on railway rout of Tehran-Ahwaz on Bakhtiari river.
Construction location of Bakhtyari dam has 50 km direct distance from upstream of Dez dam and 5 km distance from upstream the Sezar and Bakhtiari rivers’ cross section.
River specifications
Bakhtiari River is one of the main branches of Dez River which originates from the southern heights of Oshtorankooh Mountain and in the vicinity of Tangpanj station joins to Sezar River and forms Dez River.
Specifications of catchmnet area
Measurement of the catchment area at the site of the dam construction is about 6288 km2 and the average of catchment area height from sea level is 2212 m. Average annual discharge of Bakhtyari River at dam site is about 144.6 m3/s (according to testing period of 60 years) and average annual rainfall in this area is about 1117 mm. average slope of Bakhtiari River in its route is about 35 degrees.
Dam location
Dam locationAs it is shown in the image of project location; in the area of Karun and Bakhtiari catchment area, Bakhtiari dam will be constructed in upstream of (Dez) dam with a distance of 50 km to it.
Features
- The highest double arc dam of the world with the height of 325 m
- The biggest artificial reservoir of the country after Karkheh reservoir, with the capacity of 5.2 billion m3 at normal level
- No need to displace inhabitants of the reservoir area (due to the fact that this area is difficult to pass) after construction and water filling not many agricultural lands and no permanent village will go under water
- Power-plant capacity at 20% functional coefficient is
- 1500 W and its annual power generation is about
- 3000 GW/h
- Remarkable role of water supply and water regulation of the dam due to huge capacity of its reservoir
- Big economical indices of this project in comparison with economical indices of other projects, including hydro electric projects
- Controlling seasonal floods and improving security conditions in down stream of dam
- Preventing sediments of Bakhtiari river to enter dam reservoir and as a result increasing the profitable life-time of Dez dam and power-plant
- Remarkable increasing of water supply capacity in catchment area for better management of water resources and increasing volume of regulated water and as a result increasing the area of agricultural lands in downstream
- Possibility of generating the optimum energy in daily and annual peak periods of energy consumption
Side Effects
Bakhtiari dam and power-plant project, during implementation, will have important effects on regional job creation by employing regional man-power. Improvement of social, economical and cultural conditions in the region, providing opportunities for development and investment, improving the welfare level of the regional inhabitants, promoting the educational and health level and increasing the annual income, better use of tourism attractions of the region, increasing the share of the region in development of the country, improvement of the land transportation through access roads and increasing the added value of services in the region will be some of economical, cultural and social effects of this national project.
In this section the project basic information is presented in form of following items:
Topography
- Meteorology
- Hydrology
- Flood
- Water quality
- Sedimentation
- Planning the water resources
- Geology
- Seismicity
- Dam reservoir
Topography
River length is more than 300 km and Bakhtiari dam has a catchment area of 6388 km2.
Item | Quantity |
Catchment area | 6388 km2 |
Average height of catchment area | 2212m |
Catchment area slope | 35% |
Average slope of the river | 5.65% |
Length of main river | 300 km |
Meteorology
Item | Quantity |
Average annual rainfall in catchment area | 1117 mm |
Average evaporation of reservoir | 1780 mm |
Average annual temperature of dam construction site | 21.2 °C |
Probable maximum rainfall (PMP) | 144 mm |
Within the catchment area there are 5 meteorology stations, which although they do not have similar outputs, but generally their situation are estimated to be desirable.
Hydrology
The studied regional stations include Taleh Zang Dez, Tangpanj Sezar, Tangpanj Bakhtiari, Sepid Dasht Sezar, Zaz, Zard Fahrah, Ghelyan and Kazem Abad Kakolestan.
Item | Quantity |
Catchment area | 6388 km2 |
Concentration time | 35 h |
Average slope of the river | 35% |
Average outflow of water in Tangpanj station | 144.6 m3 |
Flood
According to the existing data achieved from floods, most of the floods have taken place in spring and fall. The biggest observed flood in Bakhtiari River had a discharge of 4988 m3/s and occurred in Azar of 1994. Estimated discharge of floods with several return periods is presented in the following table:
Return Period | 2 | 25 | 100 | 1000 | 10000 |
Peak discharge (m3/s) | 2489 | 3910 | 5043 | 6857 | 8641 |
Water quality
Quality of Bakhtiari River water with ER and TDS are orderly 1090 maximum and 376 for drinking and agricultural use.
Sedimentation
Annual sediments volume of the area is estimated about 9 million m3.
Planning the water resources
Item | Quantity | Unit |
Normal figures | 830 | masl |
Minimum figures | 785 | masl |
Reservoir minimum volume | 2722 | mmm |
Reservoir volume at normal figures | 5200 | mmm |
Reservoir profitable volume | 2122 | mmm |
Annual inlet volume | 4307 | mmm |
Water regulation volume | 3688 | mmm |
Safety functional coefficient | 21 | % |
Power house installation capacity | 1500 | Mw |
Primarily annual energy | 2368 | GWH |
Secondary annual energy | 617 | GWH |
Output | 92 | % |
Geology
The project location is wrinkled at north-west of Zagros sedimentary catchment area and is situated in Dezful low lands. This structure is situated mostly on Silica-lime of serok Sazand. Some of the important geological structures of the area are Gir Yoveh & Sia Klooh anticline, F1, F2 and F3 faults and kink bands. The penetration amount in left side is somehow high. Seismic topography tests results shows average velocity of 3200 to 2700 m/s in abutment and 500 m/s at foundation, which are not due to stone mass quality. Underground and galleries explorations and grouting tests are being carried out.
The soil mechanic tests for determining the module of shape alternation and other physical specifications of stone mass are also being carried out.
Seismicity
Bakhtiari dam seismocity parameters are studied regarding seismography data of the region and general behavior of Zagros. With use of Deterministic method and Probabilistic method, the maximum amount of land horizontal velocity for
50-year return period (CE) is 0.15g, 145-year return period (OBE) is 0.23 g, 475-year return period (DBE) is 0.32 g and for 2000-year return period (MDE) is 0.45g. Maximum acceptable earthquake (MDE) for F3 fault is equal to 0.55 g which is equal to the vertical velocity of 0.429.
Dam reservoir
Item | Quantity |
Total volume of reservoir | 5200 million m3 |
Profitable volume of reservoir | 3027 million m3 |
Water normal level | 830 masl |
Water minimum level | 782.2 masl |
Water maximum level | 840 masl |
Dam construction area is generally located on silica-lime Sazand of the Serok and according to the layers thickness and silica compounds, is divided into seven sub-units of Sv1 to Sv7. Some of the important geological structures are anticline of Giriveh and Siahkooh, F1-F3 trust, younger fault of F2, kink bands, forked clines and four joint systems at construction site. Slope and direction of layering slope, generally at downstream of anticline axis is N215/75 and in its upstream is N035/50. The issue of studying slope stability in current situation, without considering the artificial off-take of materials in axis area and other structures, does not show any difficulty and the abutments are stable in case of earthquake.
In this section the technical information of the project is presented in form of the following items:
1-Dam body
- Body specifications
- Reservoir specifications
- Diversion system
- Instrumentation
- Spillway
- Quarries and their specifications
2-Powerhouse
- General specifications of powerhouse
- Specifications of powerhouse equipments
- Specifications of powerhouse building
- Specifications of powerhouse outlet tunnels
- Specifications of powerhouse waterways
3-Technical specifications of post and switchyard
4-Water transfer tunnels
- Specifications of tunnels
- Intake structures
- Outlet structures
5-Access roads and bridges
6-Complementary operations
Body specifications
Item | Quantity |
Dam type | Double arc concrete |
Height from foundation | 315 m |
Crest length | 434 m |
Crest width | 10 m |
Foundation width | 50 m |
Total concrete placement of the body | 3.1 million m3 |
Specifications of sealing system | |
Sealing method | Grouting curtain |
Total length of grouting | 58 km |
Reservoir specifications
Item | Quantity |
Total volume of reservoir | 5200 million m3 |
Area of reservoir | 58.7 km |
Length of dam lake | 59 km |
Width of dam lake | 1000 m |
Normal level | 830 |
Profitable volume of reservoir | 3027 million m3 |
Diversion system
First tunnel | |
Location | Left abutment |
Length of diversion tunnels | 1151 m |
Cross section | Circular |
Tunnel diameter after lining | 12 m |
Discharge capacity | 2090 m3/s |
Type of lining | concrete |
Second tunnel | |
Location | Left abutment |
Length of diversion tunnels | 1180 m |
Cross section | U shape |
Tunnel diameter after lining | 13 m |
Discharge capacity | 1680 m3/s |
Type of lining | concrete |
Type an height of upstream cofferdam | RCC 51 m |
Type an height of downstream cofferdam | RCC 25 m |
Instrumentation
No date exists in this regard.
Spillway
Item | Quantity |
Type of spillway | Gated with tunnel |
Location | Right abutment |
Type of gates | Radial |
Numbers of gates | 2 |
Diameter of tunnel | 11 m |
Discharge capacity | 5830 m3/s |
Dimension of gates | 17.7 by 11 m |
Item | Quantity |
Type of spillway | Orifice |
Location | Dam body |
Type of gates | Radial |
Numbers of gates | 2 |
Diameter of tunnel | 11 m |
Discharge capacity | 1510 m3/s |
Dimension of gates | 6.5 by 3.5 m |
Quarries and their specifications
Totally around 3 500 000 m3 of sand material is needed for the project. In order to find the suitable quarry, it became evident that within the radius of 40 km around the dam location, no river quarry exists. Therefore three areas were considered for this purpose.
A- Excavation materials within the area of dam body
and power house:
The volume of excavation materials of dam foundation, spillways, power house will reach 2 700 000 m3, from which only 60 percent (equal to 1 600 000 m3) will be used for sand material.
B- QU1 and QU2 quarries:
These quarries are located within 2 km range of downstream of dam axis and the volume of their material reaches 3.5 million m3.
C- Upstream quarries:
This quarry is located in the area of fourth unit of Saruk Sazand (upstream of batching plant location). It has a good volume of 4 million m3 suitable material.
The results of short term chemical and physical tests is generally satisfactory and the reactions of available material are alkaline-solicit and alkaline-carbonate. Therefore long term tests are being carried out in this regard.
General specifications of powerhouse
Item | Quantity | |
Type of powerhouse | Underground | |
Location | Left abutment | |
Capacity | 1500 mw | |
Average annual generation | 3000 million kw/h | |
Turbine type | Francis with vertical axis | |
Operation level | Minimum critical | 770 |
Normal | 791 | |
Maximum | 830 |
Specifications of powerhouse equipments
Item | Quantity |
Numbers of turbine (main phase) | 6 units |
Numbers of turbine (development phase) | Being designed |
Power of each turbine | 250 MW |
Maximum output | 92 % |
Height of turbine design | 250 m |
Design discharge of each unit | 104.5 m3/s |
Numbers of generators (main phase) | 6 units |
Numbers of generators (development phase) | Being designed |
Type of generators | Being designed |
Output power of each generator | 250 mva |
Rotation speed of generator | 272.7 rotations per minute |
Specifications of powerhouse building
Powerhouse cavern | ||
---|---|---|
Length | Width | Height |
161m | 24m | 64m |
Total volume of excavation | 180 000 m3 | |
Total volume of concrete placement | Being designed |
Specifications of powerhouse outlet tunnels
In this regard no data exists.
Specifications of powerhouse waterways
In this regard no data exists.
Technical specifications of post and switchyard
Specifications of switchyard and 400 kv transfer lines | |
---|---|
Post voltage | 400 KV |
Arrangement type of post | 1.5 key |
Numbers of B | Being designed |
Intake numbers | Being designed |
Outlet numbers | Being designed |
Area of post land | 50 000 m2 |
Specifications of 400 post | |
Numbers of transformers | Being designed |
Numbers of feeders of transformers | Being designed |
Power of each transformer | Being designed |
Numbers of outlet feeders | Being designed |
Voltage of each outlet feeder | Being designed |
Specifications of tunnels
Main Phase | |
---|---|
Length of water transfer tunnel | 504 m |
Diameter of intake transfer tunnel | 8 m |
Diameter of outlet transfer tunnel | 9.5 m |
Type of lining | Concrete |
Numbers of intake penstocks | 6 |
Length of each penstock | 51 m |
Average diameters of penstocks | 6.5 m |
Development phase is being designed.
Intake structures
Item | Quantity |
Numbers of intake | 3 |
Maximum design discharge | 104.5 m3/s |
Design head | 228.5-289.3 m |
Numbers of valves | 2 series of 4 |
Type | Stop-log |
Valve of intake structure | Radial |
Width of valve | Being designed |
Height of valve | Being designed |
Outlet structures
Item | Quantity |
Numbers of intake | 6 |
Maximum design discharge | Being designed |
Design head | Being designed |
Numbers of valves | Being designed |
Type | Being designed |
Valve of intake structure | Being designed |
Width of valve | Being designed |
Height of valve | Being designed |
Access roads and bridges
A- Internal access roads
1-Technical specifications of internal access roads
Name of the road | Average width (m) | Length (km) |
Downstream road | 9 | 8 |
Access road to crest and site stabilization area | 9 | 10 |
2- Technical specifications of internal bridges
Name of the bridge | Width (m) | Length (m) | Type of structure |
Sezar 3 bridge | 9 | 190 | Metal sheet shaft with concrete |
Dez bridge | 9 | 150 | Metal sheet shaft with concrete |
Doab bridge | 9 | 40 | Metal sheet shaft with concrete |
Sezar 2 bridge | 7 | 100 | Metal sheet shaft with concrete |
The bridge adjacent to diversion tunnel | 6 | 90 | Roof-truss |
Entrance bridge to GL6 tunnel | 6 | 75 | Roof-truss |
B- External access roads
In order to have road access to construction location of Bakhtiari dam, Board of Managers of IWPC approved to construct an access road from Khorramabad city to Tangpanj station. The distance between Khorramabad and Tangpanj station is 112 km.
The width of the said road is 7 m and other details are being designed. This road includes the following components:
1- Khorramabad- Cheshmak with the length of 32 km, including the existing asphalt road
2- Cheshmak- Emamzade Seyed Ali with the length of 25 km, including the existing road which need asphalt lining
3- Emamzadeh Seyed Ali- Tanghaft with the length of 35 km, 20 km of which is rehabilitation of the existing road and the rest should be constructed
4- Tanghaft- Tangpanj with the length of 20 km, that should be constructed
Complementary operations
In this regard no data exists.